Civilengineer friend no one website Civil engineering Subjects tutorial Learn Civil Engineering online Building construction Building material Bricks Cement Concrete technology Irrigation engineering R.C.C. Structure design Limit State Method Working Stress method Strength of material SFD and BMD Surveying Theory of structure Architects I Engineers I Developer Assure Quality With Excellence

test banner

Tuesday, 31 December 2019

PPC or OPC And Their Difference

PPC or OPC

difference between opc and ppc cement,opc vs ppc difference,difference in opc & ppc,opc and ppc full form,difference between ppc and opc,cement differences between opc and ppc cement,opc vs ppc cement,difference between opc 43 and opc 53,difference between ppc and psc cement,difference between psc and ppc cement,which cement is better opc or ppc,opc and ppc

OPC = Ordinary Portland Cement PPC : Pozzolonic Portland cement (FYI : PPC is environment friendly as it consists y ash in some specic percentages by parts, which is a waste product of burnt coal, usually collected from thermal power plants) OPC (m53) attains strength in a shorter time, while PPC (m43) takes longer. OPC therefore dries more quickly, but produces more heat during chemical reaction during which it gains strength, as compared to PPC Faster is the drying process, more is the risk of cracking of cement, and therefore it need more care and more amount of water for curing in a lesser time. PPC on the other hand can attain strength equal to OPC, but takes a longer time. For a building slab, PPC is more widely used since it requires less care. The strength depends on design mix (the water cement and aggregate ratio) more than type of cement. so essentially, If you need construction to take place faster and have means for good curing, you may use OPC. But if you need better quality and strength in less eort, use PPC. It still depends on the structure’s design requirements and a structural designer’s advice is to be followed.

PPC is economically better than OPC. Strengthwise , PPC is always grade 33 ( although this is never mentioned on the bag ) whereas OPC is availabie in grades 43 & 53. The setting process of PPC is slower than OPC and hence the striking o period for the form work gets extended by about 50%. PPC has a relatively low heat emission process as compared to OPC and hence the ner shrinkage cracks which are normally seen on fresh RCC slab cast with higher grade cement are not seen with PPC. In case , a nominal mix is used for the concrete ( say 1:1.5: 3 ), which assumes grade 33 cement is used , PPC matches the strength requirements. If design mix is opted , the laboratory does consider the exact strength available from the specic brand/ grade of cement being deployed . Thus use of OPC or PPC cement shall be properly weighed in the design mix.

Difference Between OPC and PPC

In the following table the main differences between OPC and PPC cement are given:
SourcesShallow FoundationDeep Foundation
1Definition/ ComponentsA mixture of limestone and other raw materials like argillaceous, calcareous, gypsum is prepared and then grinded to prepare OPC.PPC is prepared by adding Pozzolanic materials to OPC. So, the main components are OPC clinker, gypsum and pozzolanic materials (15~35%) which includes calcined clay, volcanic ash, fly ash or silica fumes.
2StrengthInitial strength is higher than PPC.PPC has higher strength than OPC over a longer period of time.
3Heat of hydrationGenerates more heat than PPC in hydration reaction which makes it less suitable for mass casting.It has a slow hydration process and thus generates less heat than OPC.
4DurabilityLess durable in aggressive weather.More durable in aggressive weather.
5CostCostlier than PPC.Cheaper than OPC.
6Environmental ImpactEmits CO2 during the manufacturing process.It constitutes industrial and natural waste which makes it eco-friendly.
7Application/ usesIt is suitable where fast construction is required but not suitable for mass concreting due to heat issue as mentioned above.It is suitable for all types of construction work. For example RCC casting of buildings, mass concreting for bridges and even plastering and other non-structural works.
8Setting TimeLower than PPC. Its initial setting time is 30 minutes and final setting time is 280 minutes. Its faster setting time helps faster construction.Setting time of PPC us higher than OPC. Its initial setting time is 30 minutes and final setting time is 600 minutes. Its slower setting time helps to get better finishing.
9FinenessOPC has finiteness of 225 sq.m/kg. It has lower fineness than PPC. So, it has higher permeability resulting lower durability.OPC has finiteness of 300 sq.m/kg. It has higher fineness than OPC. So, it has lower permeability resulting in higher durability.
10Grades available33 Grade, 43 Grade, and 53 Grade OPC cement are available.No specified grade of PPC cement is available.
11WorkabilityLower than PPC.Higher than OPC.
12Resistance against chemical attackIt has lower resistance against alkalis, sulphates, chlorides etc.It has higher resistance against alkalis, sulphates, chlorides etc.

Read More:

What is Cement? What are the types of cement and their uses?

Composition of Cement clinker and Hydration of Cement 

Types of Tests on Cement to Check the Quality

PPC or OPC And Their Difference

All Types of Cement in Construction

Must-Know Points to Check on a Cement Bag Before Buying It


No comments:

Post a Comment

If you are getting more information from civilengineerfriend page please give your comments. Share the page information in your whatsapp group. Subscribe our page to get more information.