Civilengineer friend no one website Civil engineering Subjects tutorial Learn Civil Engineering online Building construction Building material Bricks Cement Concrete technology Irrigation engineering R.C.C. Structure design Limit State Method Working Stress method Strength of material SFD and BMD Surveying Theory of structure Architects I Engineers I Developer Assure Quality With Excellence

test banner

Thursday 4 July 2019

What is the minimum curing time for cement concrete?

What is the minimum curing time for cement concrete?
The period of curing of concrete is most important as it is very essential for keeping the hydration process of cement until concrete attains the maximum compressive strength, which increases but slowly after 28 days from initial placing time.
curing,what is the curing time for a pillar,curing of concrete,time period for curing cement,what is the meaning of accelerated curing,what is plain cement concrete,curing time,what is the definition of accelerated curing,concrete curing time calculator,concrete curing time,what are the ingredients in plain cement concrete,minimum curing time,ideal temperature for cement curing

Compressive strength reduces to 50%, If it would be in air without curing.From the above figure, you can analyze that moist curing is essential for concrete to achieve the approximate maximum strength (Not 100%). Ideally the curing period depends upon the type of cement used, mixture proportions, required strength, size and shape of member, ambient weather, future exposure conditions, and method of curing.

The period should be as long as practical. Environmental temperature plays very big part in the process of curing as the hydration process is an exothermic reaction. Maintaining proper temperature is also very important and it affects the duration of curing. For most concrete structures, the curing period at temperatures above 5º C should be a minimum of 7 days or until 70% of the specified compressive or flexural strength is attained. The period could be reduced to 3 days if high early strength concrete is used and the temperature is above 10º C.
As the early strength of concrete is supportive towards the ultimate strength of concrete, we should do proper curing according to the environment condition, type of member etc.
So 7 days, in normal condition. But there is never a thing called normal. So, considering all uncertainties, 10 to 12 days of curing with proper method like ponding, gunny bag, sprinkling etc. has to be done to ensure almost 80% of the ultimate strength of concrete.