Civilengineer friend no one website Civil engineering Subjects tutorial Learn Civil Engineering online Building construction Building material Bricks Cement Concrete technology Irrigation engineering R.C.C. Structure design Limit State Method Working Stress method Strength of material SFD and BMD Surveying Theory of structure Architects I Engineers I Developer Assure Quality With Excellence

test banner

Thursday, 4 July 2019

Shuttering removal time of different structural members

Shuttering removal time of different structural members

Shuttering is the set of forms required to keep the concrete in place until it sets. In case you want to know about shuttering and how it is provided ? 
deshuttering period of slab,shuttering,checklist for shuttering,forms of concrete slab when to remove,de shuttering of slab,deshuttering period of column,de shuttering of rcc slab,removal of formwork time,forms of concrete slab when to deshutter,shuttering of beam and slab,forms of concrete beam when to remove,how to check slab shuttering,when to remove concrete formwork
How shuttering is provided ? 
Shuttering removal time of different structural members is given below:

time with ordinary Portland cement used

  • Beam sides, walls and columns required 2-3 days.
  • Slab sides required 3 days.
  • Complete slab shuttering should be removed after 10 days.
  • Beams removal of sheeting required 8 days.
  • Beams and arches complete removal of shuttering required 14 days.
  • If beams and arches are of span more than 6 meter, then shuttering removal time should be 21 days.

Shuttering removal time with Rapid hardening cement used

  • Beam sides, walls and columns required 2 days.
  • Slab sides required 3 days.
  • Complete slab shuttering should be removed after 5 days.
  • Beams removal of sheeting required 5 days.
  • Beams and arches complete removal of shuttering required 5 to 8 days.
  • If beams and arches are of span more than 6 meter, then shuttering removal time should be 8 to 10 days.